File #: Item # 2019-170    Version: 1 Name:
Type: Resolution Status: Passed
File created: 9/9/2019 In control: Town Council
On agenda: 9/18/2019 Final action: 9/18/2019
Title: A RESOLUTION OF THE MAYOR AND TOWN COUNCIL OF THE TOWN OF CUTLER BAY, FLORIDA, APPROVING AN AGREEMENT WITH ENVIROWASTE SERVICES GROUP, INC. FOR MISCELLANEOUS ROADWAY AND DRAINAGE IMPROVEMENTS; PROVIDING FOR AUTHORIZATION; AND PROVIDING FOR AN EFFECTIVE DATE.
Attachments: 1. Manager Memo-Award ITB 19-08 Misc Roadway and Drainage Improvements, 2. Manager Memo-Attachment A-Advertisement-Daily Business Review, 3. Manager Memo-Attachment B-Pre-Bid Meeting Sign-In Sheets, 4. Manager Memo-Attachment C-Summary of Bid Opening, 5. Manager Memo-Attachment D-Bid Submittal Review, 6. Manager Memo-Attachment E-Bidder Submittal Package, 7. Resolution-Award of ITB 19-08 Misc Roadway and Drainage Improvements, 8. Resolution-Exhibit A-Misc Roadway and Drainage Improvements Contract



M E M O R A N D U M

To: Honorable Mayor and Town Council

From: Rafael G. Casals, ICMA-CM, CFM, Town Manager

Date: September 18, 2019

Re: Award of ITB # 19-08: Miscellaneous Roadway and Drainage Improvements


REQUEST
title
A RESOLUTION OF THE MAYOR AND TOWN COUNCIL OF THE TOWN OF CUTLER BAY, FLORIDA, APPROVING AN AGREEMENT WITH ENVIROWASTE SERVICES GROUP, INC. FOR MISCELLANEOUS ROADWAY AND DRAINAGE IMPROVEMENTS; PROVIDING FOR AUTHORIZATION; AND PROVIDING FOR AN EFFECTIVE DATE.
title

BACKGROUND AND ANALYSIS

As a result of the Road Transfer Agreement, adopted by Resolution No. 08-11, between Miami-Dade County (the "County"), the ownership of all the local roadways, was transferred to the Town of Cutler Bay (the "Town"). As a result of the Town opting-out of the County's Stormwater Utility (Resolution No. 07-18), the existing storm drainage structures were all transferred to the Town. The Town's adopted Stormwater Utility Master Plan (Resolution No. 08-50), has identified several neighborhoods with localized flooding in need of drainage improvements. Throughout the past years, the Town's Public Works Department (the "Department") has performed repairs to numerous roadway and drainage structures, which have been reported by residences and/or discovered through route patrol, by staff.

On June 18, 2019, the Town issued Invitation to Bid (ITB) No. #19-08: Miscellaneous Roadway and Drainage Improvements. The ITB was advertised in a newspaper of general circulation (Attachment "A"), which complies with the Town's Code Chapter 24, Article II. A Mandatory Pre-Bid Meeting was held on July 9, 2019 at 10:00 AM, at which time twelve (12) potential bidders were in attendance (Attachment "B"). The ITB's due date and time was August 8, 2019 at 3:00 PM. The Town received five (5) sealed bid packages from potential contractors, which were publicly opened at Town Hall (Attachment "C").




A comprehensive Bid Submittal Review was completed by the Town's Public Wor...